Producing or conducting well intervention operations in adjacent wells during drilling operations is a potentially hazardous situation.  In simultaneous drilling/production operations a risk management approach is accepted as being the best way to address the problem.

 

The following table addresses the most critical activities during drilling operations and identifies the risks, mitigating actions and responsible paths

 

Operation

Hazard

Consequences

Conditions and Controls

References

Drilling 26in hole
Setting 20 in casing

Drilling 16in hole
Setting 13.3/8in casing

Dropped object


Intersection with adjacent wells, shallow gas

Damage to process equipment, release of hydrocarbons, H2S exposure, injury to personnel working in the vicinity. Possible fire or explosion

Adjacent wells will remain secured with downhole plug SCSSV, BPV

Flowline will remain de-pressurised within the collision risk zone (100 ft radius)

Area access restriction

COMPANY Drilling Manual

H2S Contingency plan

Well Control Manual Contingency

Plan and Emergency Well Control Manual

Heavy lift Operations over wellbay eg, risers, BOP’s, wellheads and Xmas tree

Welding
Torch cutting

Dropped object




Fire / Explosion

Damage to process equipment, release of Hydrocarbons, H2S exposure, injury to personnel working in the vicinity

Closure and de-pressurisation of adjacent wells until lifting operations are complete. (De-pressurisation in this case includes tubing above SCSSV, Xmas tree and flowlines)

Permit to work system

Area access restricted

Pre-job safety meeting

P.A. announcement

Well Control Manual

COMPANY Contingency Plan and Emergency Procedure

H2S Contingency Plan

Perforating

Stuck Pipe

Fishing

Premature detonation of explosive charge

Serious explosion, personnel injury

Suspension of hot work

Area access restriction

Radio silence. Local Rules

P.A. announcement

Stray Current Control

COMPANY Contingency Plan and Emergency Procedure

Radio Silence Standing Instructions

Acidizing
Nitrogen lifting

Loss of well control

Splash/spill release

Release of hydrocarbons, H2S, exposure, fire or explosion Injury to personnel

No hot work on WHJ or cantilever superstructure

Closure of adjacent wells

Safety clothing

Emergency wash stations

Area access restriction

Wellbay area to be marked area to be marked with Hazard tape.

Completion Programme

COMPANY Contingency Plan and Emergency Procedure

H2S Contingency Plan

Well testing

Relief valve on separator pops out extinguishing flare from burner

Release of hydrocarbons from atmospheric vent boom H2S exposure, fire or explosion

This operation only permitted with written approval from Drilling Department

COMPANY Contingency Plans and Emergency Procedure

Pressure testing and BOP testing except testing equipment lines

Failure of mechanical component

Liquid jet impact, projectiles, injury to personnel

P.A. announcement.

Area defined by components under test to be restricted by use of Hazard tape.

Utilisation of certified ‘fit for purpose’ components

Drilling Manual

COMPANY Contingency Plan and Emergency Manual

Drilling 12.1/4in hole
Setting 9.5/8in casing
Drilling 8.1/2in hole beyond 100ft radius of collision

Running tubing

Loss of well control

Release of Hydrocarbons

H2S Exposure, possible fire or explosion

Not hot work on WHJ or cantilever substructure. Should the BOP’s be activated in the event of an emergency then the producing wells should be closed immediately by activating the ESO.

Drilling Manual

COMPANY Contingency Plan and Emergency Procedure

H2S Contingency Plan

Operations with Radioactive Sources
Open hole logging

Release or exposure to radiation

Injury of illness to personnel exposed to hazard

Area access restriction, monitor area

Pre-job safety meeting

P.A. announcement

COMPANY Contingency Plan and Emergency Procedure