- Remove casing hanger running tool by rotating to the right (approx 14 turns).
- Change out bail arms on top drive.
- RIH one joint of drill pipe. Clean out BOP and wellhead area. POOH
- RIH with KIOS flushing tool and jet on top of the casing hanger neck.
- Clean out wellhead. POOH.
- RIH setting tool and set MST seal assembly. Pressure test to 500 psi for 15 mins.
- Nipple down BOP.
- Nipple up 13 5/8” x 11” 10k tubing spool and test to 5000 psi for 15 mins.
- N/U 13-5/8” BOPs
- Install test plug.
- Do not install O ring until after pulling tool has been turned over to use as test plug.
- Test BOPs
- Annnular: 300 psi 5 min \ 3500 psi 10 min
- Rams: 300 psi 5 min \ 5000 psi 10 min
- TIW valves, IBOP, Stand pipe manifold: 300 psi 5 min \ 5000 psi 10 min
Note: choke and kill manifold valves to have been tested off line:300 psi 5 min \ 5000 psi 10 min
Blind rams to have been stump tested off line
- If salt saturated mud is used, ensure to flush/ clean all lines from salt crystals and cutting to avoid lines getting plugged up
- Ensure to consider jetting and washing wellhead and BOP prior to removing Bell Nipple to eliminate the chance of getting junk or cuttings to fall from pollution pan into BOP
- All pressure tests shall be recorded on chart and include the volume pumped to reach the test pressure and the volume bled back. Test recording charts and other documents shall be filed at the rig site by the Rig contractor superintendent. Copies of all test charts and other documents shall be sent to the Drilling Superintendent in office.
- While running in the NBP pulling tool to pull out; the steamer could be utilized to ensure the side valves are not frozen.
- Run and install the wear bushing with the WB combination running tool according to ABB Vetco Grey procedures.