This article describes the reports required to be submitted by the contractor to the Company Completion Supervisor.
Well Completion Equipment Report
Contractor shall submit to the Company Completion Supervisor, detailed assembly drawings of all sub assemblies clearly identifying the make up lengths required for space out calculations prior to mobilisation.
Contractor shall submit a detailed well completion diagram showing all relevant lengths, depths and individual tool dimensions to the Company Completion Supervisor, as soon as possible following each well completion.
Well Completion Daily Report
During offshore operations, the Contractor representative shall plan, monitor, and report to the Company Completion Supervisor, the operational progress of the work on a daily basis complete with suitable schedule diagrams and reporting formats. They shall submit a Daily Performance Report to the Company Completion Supervisor detailing the current job status and shall include all relevant information.
Company provided formats for reports shall be utilised, where available.
Well Completion Work Report.
Contractor shall provide a work report to the Company Completion Supervisor, upon completion of the work. This work report shall take the form of a post job evaluation and shall include an accurate time breakdown and detailed sequence of events for the entire completion period.
Contractor shall submit as part of the Work Report, an equipment performance summary detailing equipment downtime, if any, reasons for downtime and corrective action taken.
The Work Report shall be submitted as soon as possible following the completion of the work.