- weatherford – 2 tongs & power units. Both 20” and 13/38
- rio negro grouted
- drains / channels preferably clear prior to spotting equipment
- 40” casing to cut. And corregate walls on cellar, cut out
- cellar to empty to locate the flyge pump sump. Install pump and hook up same
- mouse hole and rathole, in place
- pipe bins in place
- casing in place and strapped. All casing running tools ready
- chicksans connected to stand pipe, at subbase
- flare line. & degasser hooked up
- baryte recovery line hooked up
- stairs on pits installed
- trip tank pump
- totco wire line unit ready to go
- general rig floor rig up, tongs..etc
- totco geolograph recorder
- drilling line spooler
- primary check on bop’s
- spud mud ready + extra water in other tanks
- cementing ready, all lines rigged up silo’s full
- mudlog ready
- solids control ready
- barytes on location, silo’s full
- trash bins in plac
- pick up & make up two stands of hwdp & set in mast
- stab in tool checked, d/p centralisers
- false rotary. Etc
- 20” strapped + cleaned. Check stab in tool required
- channels cut in shoe + shoe made up on first joint run
- welding equipment ready + on stand by
- riser chains ready
- wooden mats out for drilling tools
- spacer spool installation on the bottom of 13 5/8 bops
- wash down guns rigged up
- install submersible pump in water pit and hook up and test same
- water well generator still on independent power
- weighted bucket on choke manifold flare line
- handrails to install between brine pit and obm tank walk way
- electrical panel to close at brine skid
- cable tray covers to install
- trip tank hose to hook up
- flow line to hook up
- bha to lay out and strap
- 20” casing to lay out and strap – i nstall shoe and cut out channels
- crown ‘o’ matic to install
- respot drill line spooler skid
- remove bop work platform to other side
- spreader beams on rig cantilever to remove and stow away
- open drainage channels from cellar deck to rio negro
- casing stabbing board to install and test
- lay out 20 riser by racks – check all turnbuckles and chains are working and lubricated
- hook up choke line to manifold – if you have time
- general drilling tools and casing to get ready
- have the 3 1/2 “ rams been replaced by 5”?
- 40” casing to cut off level with ground. Cut slots in cellar wall
- jet line to install
- check all chains and turnbuckles are functioning for holding down the 20” casing
- 20 casing to lay out, clean and measure and shoe to install. Channels to cut in shoe joint
- bha to lay out, rabbit and measure. Record stabilizer blade gauges.
- drains and ditches to clear of all obstructions
- rio negro. Is the chute properly installed to carry cuttings away?
- cable tray covers to install
- totco barrel on slick line
- geolograph hooked up
- submersible pump at waterpit to install and hook up - test same
- flare line off choke manifold to hook up
- poor boy degasser line to complete.bop platform on back side to install so flowline can be hooked up on surface pipe.
- 2 stands of hwdp in derrick prior to spud
- koomey unit to install at location
- ditches between pits to grout with old cement
- ensure the flowline to derrick shakers is clean, to allow the flow of cuttings to the end derrick shaker
- Prior to acceptance pressure test the rig pumps against kelly to 3000psi each pump, just to check the integrity of the connections.
- Cut a few of meters of formation to test the whole system (1x kelly down).