Checklist for Drilling Supervisor |
|||
# |
Time |
Description |
Post-job remarks |
1 |
5d |
Cement proposal checked/acceptable. |
|
2 |
3d |
Cementer called out. Competence verified through the Contractor Base Manager. |
|
3 |
2d |
Proposal approved by ODE/1X. |
|
4 |
6h |
Tasks appointed; Scenario ready. |
|
5 |
6h |
Diagram of all lines / valves OK and checked. |
|
6 |
6h |
Annotated execution flow chart ready. |
|
7 |
1h |
Hole OK. (Clean, losses cured, overbalance OK). |
|
8 |
1h |
Mud OK (Rheology in spec., mud mobility in annulus maximised). |
|
9 |
1h |
Mixwater and spacer checklist OK. |
|
10 |
1h |
Rig Eqt. OK. (Compressor, Transfer-and Mud Pumps, Silo's) |
|
11 |
1h |
Cement Eqt OK. (Cmt Unit, Cmt head, Surface/ Lines) |
|
12 |
1h |
Plugs and launcher OK (plugs, P test, Ids of cocks, XO, DP, etc. for liner). |
|
13 |
1h |
Safety Eqt OK. (Dusk mask, Goggles, Earplugs, Gloves, Eye Wash, Fire Fighting) |
|
14 |
1h |
All involved Personnel briefed; 'What if' discussed with key personnel. |
|
15 |
1h |
Check lines/valves (tanks, cmt unit, surface (P test), return) |
|
16 |
5d |
Send samples of water, cement and additives to lab . Label |
|
17 |
5d |
Send cementation form to lab. Preliminary recipe received. |
|
18 |
2d |
Received recipe for cement and weighted spacer from lab. |
|
19 |
2d |
Prepare cementation programme. |
|
20 |
1d |
Update cement programme with caliper and temperature from logs. The Lab must be informed of any variation from |
|
21 |
1d |
Compare job calculations with those of Cementer. |
|
22 |
2h |
Perform circulation test. Establish pressure at bump rate. |
|
23 |
1h |
Dust mask, gloves and ear and eyes protection, eye wash. |
|
Checklist for Mud Engineer |
|||
# |
Time |
Description |
Post-job remarks |
1 |
1d |
Fill mixing tank with water to required level and check chlorides <400 ppm. |
|
3 |
1d |
Check quantity of additives as they are added to tank. Record quantity and sequence. |
|
4 |
1d |
Record level of mix water tank after adding additives |
|
5 |
1d |
Perform bench test with mix water with representative cement sample. |
|
6 |
2h |
Check that the mud rheology is within specifications of the Well Programme. |
|
7 |
2h |
Calibrate time gradient with pressurised mud balance plus back-up standard mud balance. |
|
8 |
1h |
Check level of mix water tank prior to cementing for any evidence of contamination. |
|
9 |
1h |
Water bath set at correct temperature. |
|
Checklist for Rig Equipment by Drilling Contractor |
|||
# |
Time |
Description |
Post-job remarks |
Air Compressor |
|||
1. |
|
Power end. |
|
2. |
|
Pressure. |
|
3. |
|
Volume. |
|
4. |
|
"Dryness". |
|
5. |
|
Relief valve. |
|
6. |
|
No leaks in system (last test date/pressure). |
|
Transfer pump |
|||
1. |
|
Impeller check (dry run). |
|
2. |
|
Leaking shaft seals (false air). |
|
3. |
|
Electrical switches. |
|
4. |
|
Lines flushed. |
|
Mud pumps |
|||
1. |
|
Relief valve (pressure test). |
|
2. |
|
Control power supply, switches. |
|
3. |
|
Pistons OK (pre job cleaned). |
|
4. |
|
Liners OK (pre job cleaned). |
|
5. |
|
Valves OK (pre job cleaned). |
|
6. |
|
Suction lines/strainers (pre job cleaned). |
|
Tanks |
|||
1. |
|
Line up to cement unit OK. |
|
2. |
|
No leaks on tank or valves. |
|
3. |
|
Level indicators OK. |
|
Surface lines |
|||
1. |
|
Pressure test . |
|
2. |
|
Size adequate (avoid bottlenecks). |
|
3. |
|
Cement dump line operational. |
|
4. |
|
Ensure that valves in lines are in good condition. |
|
Manifold |
|||
1. |
|
Hook up as on diagram. |
|
2. |
|
Integrity of the valves OK. |
|
3. |
|
Check lines (flushed/clean). |
|
4. |
|
Contingency lines clean and ready for hook up. |
|
Return line |
|||
1. |
|
Lined up as per diagram. |
|
2. |
|
No Leakage’s into line from outside |
|
Cement silo's |
|||
1. |
|
Pre fluff and circulate around. |
|
Surge tank |
|||
1. |
|
Maintain pressure differential. |
|
Checklist for the Cementer |
||||||
# |
Time |
Description |
Post-job remarks |
|||
General |
||||||
1. |
|
Job calculations done. |
|
|||
2. |
|
Chemicals quality and quantity checked. |
|
|||
3. |
|
Dust mask, gloves and ear, eyes protection; fire extinguisher, eye wash station. |
|
|||
Pre-Job |
||||||
1 |
|
Check quantity / appearance of cement and additives |
|
|||
2 |
|
Flush lines from mix tank to cement unit with water |
|
|||
Cementing unit |
||||||
1. |
|
Air system - check air cleaner, lubrication, tanks and drain moisture. |
|
|||
2. |
|
Diesel fuel - check level, drain water and sediment from bottom. |
|
|||
3. |
|
Engine oil - check level twice for consistency. |
|
|||
4. |
|
Radiator/heat exchanger - water level. |
|
|||
5. |
|
Fire hose for cooling engine stand-by. |
|
|||
6. |
|
Fan belt - tension, crack or damage. |
|
|||
7. |
|
Transmission oil - check level. |
|
|||
8. |
|
Chain case oil - check level. |
|
|||
9. |
|
Power end oil - check level. |
|
|||
10. |
|
Hydraulic oil - check level. |
|
|||
11. |
|
Plunger oiled - check reservoir tank level and alemite pump. |
|
|||
12. |
|
Gauges - check for operation. |
|
|||
13. |
|
Emergency kill system - check operation. |
|
|||
14. |
|
Pneumatic operating butterfly valves - check operation. |
|
|||
15. |
|
Centrifugal pumps - bearing oil level, packing seal, impeller (dry run), |
|
|||
16. |
|
Output pressure and rate. |
|
|||
17. |
|
Pressure sensor diaphragm - pumped up and leak-free. |
|
|||
18. |
|
Start engine - check starter. |
|
|||
19. |
|
Circulation - check for strainer, suction and discharge lines. |
|
|||
20. |
|
Valves condition. |
|
|||
21. |
|
Over pressure shutdown system - check operation by pressuring. |
|
|||
22. |
|
Pressure test - test unit to 1,000 psi. above expected working pressure. |
|
|||
23. |
|
Sensors - pressure, gradient and flow rate, calibrate if necessary. |
|
|||
Re-circulating mixer |
||||||
1. |
|
Slurry tub - strainer, clean and cement-free. |
|
|||
2. |
|
Knife gate (metering valve) - check operation, grease. |
|
|||
3. |
|
Mixing bowl - correct jets size. |
|
|||
4. |
|
Centrifugal pump - check for output pressure and rate, leaks on seal, wear in bearing |
|
|||
5. |
|
Check operation of cement, water quick shut off valves & recirculating valve. |
|
|||
Batch Mixer |
||||||
1. |
|
Centrifugal pump - check for output pressure and rate, leak on seal, wear in bearing |
|
|||
2. |
|
Paddle - operational. |
|
|||
3. |
|
Electric motor - cables, switches, coil resistivity test. |
|
|||
4. |
|
Chemical hopper - clean, jets good, lines clear. |
|
|||
5. |
|
Dry cement inlet - clean and operational. |
|
|||
Surge Can |
||||||
1. |
|
Check can clean and empty. |
|
|||
2. |
|
Pre fluff through air jets and blow clear through vent line. |
|
|||
3. |
|
Check all gauges, zero the gradient indicator. |
|
|||
4. |
|
Load cell - pumped up, leak-free. |
|
|||
5. |
|
Sight glasses - clean and not cracked. |
|
|||
6. |
|
Hatch cover - hinges, bolts secured, leak-free. |
|
|||
7. |
|
Relief valve - check last serviced and tested. |
|
|||
8. |
|
Check all lines, jets, hoses and check valves. |
|
|||
Cementing heads |
||||||
1. |
|
Correct size - pressure rating (stump test). |
|
|||
2. |
|
Manifold valves - greased, pressure tested. |
|
|||
3. |
|
Plug retainers - greased, operation. |
|
|||
4. |
|
Plug release indicator - operation. |
|
|||
5. |
|
Cross-over - ‘o’ rings, correct thread. |
|
|||
6. |
|
Circulating heads - non welded, pressure rating. |
|
|||
7. |
|
Check quantity/appearance of cement and additives |
|
|||
|
|
|
|
|||
|
|
|
|
|||