- 8 ½” bit, nozzles, tool and breaker
- Bit hand on location
- Test plug ready
- Install wear bushing
- Float valve installed
- BHA on racks and strapped
- Stabilizers, jars strapped and ready to RIH
- Mud man to ensure OBM dilution is as per programme
- Make space and clean tanks. Mix brine, spacers to program specs
- Schlumberger logging required prior to liner job
- Request liner delivery (ex HMD), strap, clean and rabbit same
- Install liner consumables as per program
- Have additional bakerlock on hand
- Drill pipe plug launcher head
- Call out Baker hand for running liner whilst logging
- Check all dimensions with Baker hand
- Call out pickup/laydown machine
- Call out casing crew +/- 2 days prior to running liner. Check csg tongs, pwr packs
- Batch mixer required for liners (1day prior), check cmt on location
- Core heads for 8½” section
- Pup jts for coring
- Core barrels and inner barrels (fibre glass or not?)
- Core boxes
- Call out core hand +/- 2 days prior to running
- Mud man to be ready for displacement to brine
- Check if a 5”x3½” string or all 3½” is to be used
- Clean out string for liner
- Clean-out jewellery and bit
- Tubing adapter flange, X-mas tree/suspension tree prepared
- Schlumberger & vibro truck
- Run flare lines
- Break kelly prior to laying out
- Have transport baskets etc for SH-OO equipment ready