checklist

  • 8 ½” bit, nozzles, tool and breaker
  • Bit hand on location
  • Test plug ready
  • Install wear bushing
  • Float valve installed
  • BHA on racks and strapped
  • Stabilizers, jars strapped and ready to RIH
  • Mud man to ensure OBM dilution is as per programme
  • Make space and clean tanks. Mix brine, spacers to program specs
  • Schlumberger logging required prior to liner job
  • Request liner delivery (ex HMD), strap, clean and rabbit same
  • Install liner consumables as per program
  • Have additional bakerlock on hand
  • Drill pipe plug launcher head
  • Call out Baker hand for running liner whilst logging
  • Check all dimensions with Baker hand
  • Call out pickup/laydown machine
  • Call out casing crew +/- 2 days prior to running liner. Check csg tongs, pwr packs
  • Batch mixer required for liners (1day prior), check cmt on location
  • Core heads for 8½” section
  • Pup jts for coring
  • Core barrels and inner barrels (fibre glass or not?)
  • Core boxes
  • Call out core hand +/- 2 days prior to running
  • Mud man to be ready for displacement to brine
  • Check if a 5”x3½” string or all 3½” is to be used
  • Clean out string for liner
  • Clean-out jewellery and bit
  • Tubing adapter flange, X-mas tree/suspension tree prepared
  • Schlumberger & vibro truck
  • Run flare lines
  • Break kelly prior to laying out
  • Have transport baskets etc for SH-OO equipment ready