checklist

  • Riser centered, secure and flow line leak free
  • 26” bit, nozzles & tool on location
  • Stabilizers, x/o’s, drill collars strapped, ready
  • Totco ring inserted
  • Shock sub made ready
  • Ultra seal on location, +/- 60bbl pill mixed @ 30-40 ppb
  • Mud engineer aware of property requirements
  • Sufficient 8¼” drill collars, HWP on rack, strapped.
  • Cmt, gel & baryte . Stock on site
  • 18 5/8” csg to be drifted, threads cleaned, tally checked, number of joints on rack confirmed and numbered
  • Casing OD checked and insert correct size “FS” seals in casing head
  • 20 ¾” section “A” casing head and accessories on location.
  • Get all casing consumables to location and dress casing as per program
  • Float equipment for inner string running tool
  • 5” to 18 5/8” centralisers x 2 in stock
  • Trip tank pump functioning
  • 21¼” BOPE prepared and tested, spacer spool nippled up
  • Casing crew  and equipment on notice
  • Pick up and lay down service on notice
  • Provision for OBM supply in place