- Riser centered, secure and flow line leak free
- 26” bit, nozzles & tool on location
- Stabilizers, x/o’s, drill collars strapped, ready
- Totco ring inserted
- Shock sub made ready
- Ultra seal on location, +/- 60bbl pill mixed @ 30-40 ppb
- Mud engineer aware of property requirements
- Sufficient 8¼” drill collars, HWP on rack, strapped.
- Cmt, gel & baryte . Stock on site
- 18 5/8” csg to be drifted, threads cleaned, tally checked, number of joints on rack confirmed and numbered
- Casing OD checked and insert correct size “FS” seals in casing head
- 20 ¾” section “A” casing head and accessories on location.
- Get all casing consumables to location and dress casing as per program
- Float equipment for inner string running tool
- 5” to 18 5/8” centralisers x 2 in stock
- Trip tank pump functioning
- 21¼” BOPE prepared and tested, spacer spool nippled up
- Casing crew and equipment on notice
- Pick up and lay down service on notice
- Provision for OBM supply in place