Wear Bushing

Pull Wear Busing

Casing

Tally Casing

Pre-Install Float Shoe & Collar

 

Casing Equipment

Tongs

Spiders

Centralizers

Scratchers

Plugs

Baker Lock

Pickup Line

Fill up Line

Stabbing Board

 
 
 
 
 
 
 
 

Rig Floor Equip.

Weight Indicator

Slips

Cut & Slip Drill Line

Elevator

String Up & Back

Wellhead Service Hand

Mud Line Suspension

 
 
 
 
 
 

Procedure

Review Running Procedure

Pre Job Meeting

 

BOP

Equipment to Pick Up BOP

Spools

Spools for Riser

Emergency Packoff

Ring Gaskets

 
 

Crew

Crew Compliment

Lead Time to Call Out Equipment & Crew

 

Casing

Casing Details

Cementing

Cementing & Mixing

Contingency for Lost Circulation

Maximum Set Back

Work Platforms

Casing Dope

Running Schedule

Space Out

 
 
 
 
 
 

Tools

Casing Handling & Running Tools

Cementing Head

Swedge on Rig Floor

Drifting Casing

Check Out Running Speed

Remove All Metal Protectors

Install Teflon Quick Protectors

Emergency Contingence Plans

 
 
 
 
 
 
 

Casing Equip.

Landing Joints

Check Brake, Dynomatic

Casing Rams

Nipple Up Torque Wrench

Test Pump

Clean Threads on Float Equipment

 
 
 
 
 

Procedures

Details of Tight Spots & Doglegs

Centralizer Program

 

 

 

 

Example - Set up to run casing, with mud loggers monitoring pit gains.

  • Run csg: 
    • Float Shoe
    • jt #1
    • Float Collar
    • By-pass Baffle
    • jt #2
    • shut-off baffle
    • jt #3 . . .Jt #83
    • DV tool
    • Jt # 84. . . Jt #177
    • leave jt. #178 out
    • run jt #179 (last joint)
  • Expected stickup: 2.45 mtr.
  • Centralizers on ·Mid jt #1, ·jts #1, 2, 3, 4.
  • Casing shoe at 407 will be passed while running jt #30.
  • Switch to 350-Ton elevators after 40 joints.  Senonian Salt will be entered while running jt #45.
  • Cmt Basket on Jt #82, ·centralizer on jt #83, ·DV tool in box of jt #83, ·Centralizers on #84 - #97, 99, 101, 149, 177.
  • Record string weight ________ mt as compared to 142 mt theoretical.
  • Circulate 1 ½ times annular volume: 690 bbls, 5850 strokes, at 70 stk/min, 85 min.
  • Install plug dropping head and load 1st Stage shutoff plug if not already done.
  • Close valves and test lines to 3500 psi.
  • Open valve and pump:
  • See chart for tracking volumes**
  • Bump plug to 1400 psi over circulating pressure.
  • Check floats.
  • Open DV tool by dropping bomb, wait 15 min, and pressuring up to 1000 with cementer.
  • Circulate 4 hours at 50-70 stk/min.
  • Load 2nd Stage sealing plug.
  • Open valve and pump:
  • See chart for tracking volumes**
  • Bump plug to 1000 psi over final circulating pressure for 2 minutes.
  • Check floats.