Wear Bushing |
Pull Wear Busing |
Casing |
Tally Casing Pre-Install Float Shoe & Collar |
Casing Equipment |
Tongs Spiders Centralizers Scratchers Plugs Baker Lock Pickup Line Fill up Line Stabbing Board |
Rig Floor Equip. |
Weight Indicator Slips Cut & Slip Drill Line Elevator String Up & Back Wellhead Service Hand Mud Line Suspension |
Procedure |
Review Running Procedure Pre Job Meeting |
BOP |
Equipment to Pick Up BOP |
Spools |
Spools for Riser Emergency Packoff Ring Gaskets |
Crew |
Crew Compliment Lead Time to Call Out Equipment & Crew |
Casing |
Casing Details |
Cementing |
Cementing & Mixing Contingency for Lost Circulation Maximum Set Back Work Platforms Casing Dope Running Schedule Space Out |
Tools |
Casing Handling & Running Tools Cementing Head Swedge on Rig Floor Drifting Casing Check Out Running Speed Remove All Metal Protectors Install Teflon Quick Protectors Emergency Contingence Plans |
Casing Equip. |
Landing Joints Check Brake, Dynomatic Casing Rams Nipple Up Torque Wrench Test Pump Clean Threads on Float Equipment |
Procedures |
Details of Tight Spots & Doglegs Centralizer Program |
Example - Set up to run casing, with mud loggers monitoring pit gains.
- Run csg:
- Float Shoe
- jt #1
- Float Collar
- By-pass Baffle
- jt #2
- shut-off baffle
- jt #3 . . .Jt #83
- DV tool
- Jt # 84. . . Jt #177
- leave jt. #178 out
- run jt #179 (last joint)
- Expected stickup: 2.45 mtr.
- Centralizers on ·Mid jt #1, ·jts #1, 2, 3, 4.
- Casing shoe at 407 will be passed while running jt #30.
- Switch to 350-Ton elevators after 40 joints. Senonian Salt will be entered while running jt #45.
- Cmt Basket on Jt #82, ·centralizer on jt #83, ·DV tool in box of jt #83, ·Centralizers on #84 - #97, 99, 101, 149, 177.
- Record string weight ________ mt as compared to 142 mt theoretical.
- Circulate 1 ½ times annular volume: 690 bbls, 5850 strokes, at 70 stk/min, 85 min.
- Install plug dropping head and load 1st Stage shutoff plug if not already done.
- Close valves and test lines to 3500 psi.
- Open valve and pump:
- See chart for tracking volumes**
- Bump plug to 1400 psi over circulating pressure.
- Check floats.
- Open DV tool by dropping bomb, wait 15 min, and pressuring up to 1000 with cementer.
- Circulate 4 hours at 50-70 stk/min.
- Load 2nd Stage sealing plug.
- Open valve and pump:
- See chart for tracking volumes**
- Bump plug to 1000 psi over final circulating pressure for 2 minutes.
- Check floats.