This article describes the various responsibilities for casing running operations and quality control.
Responsibilities for casing/liner preparation, hole conditioning and mud conditioning prior to running are listed in the following table:
Action |
Execution |
Quality Control |
Ordering Casing/Liner, accessories and backup |
Equipment and Logistics Supervisor |
Operations Engineer |
Order running equipment |
Drilling Supervisor Operations Engineer |
Drilling Supervisor Operations Engineer |
Prepare casing/liner for running, i.e., drifted, thread cleaned and doped |
Drilling Contractor |
Drilling Supervisor Operations Engineer (Site) |
Determine placement of centralisers |
Operations Engineer |
Drilling Supervisor |
Prepare casing/liner running program |
Drilling Supervisor |
Drilling Supervisor Operations Engineer (Site) |
Condition hole and mud |
Mud Engineer Drilling Contractor |
Drilling Supervisor Mud Engineer |
Conduct a safety meeting for all personnel involved in the job to confirm and discuss procedures and safety precautions |
Drilling Supervisor
|
Drilling Supervisor Operations Engineer (Site) |
Casing/Liner evaluation running |
Drilling Supervisor |
Operations Engineer |
Responsibilities during casing/liner running are listed in the following table:
Action |
Execution |
Quality Control |
Make an accurate record of the string as it is installed in the well |
Drilling Contractor |
Drilling Supervisor Operations Engineer |
Run and land casing/liner including make up of connections. |
Drilling Contractor |
Drilling Supervisor |
Ensure the various weights and grades of casing/liner are run in proper sequence, that centralisers, scratchers, marker joints etc. are installed properly and are correctly positioned |
Drilling Contractor |
Drilling Supervisor |
Inspect casing/liner during running. Ensure it is made-up to the correct torque specifications |
Drilling Contractor through the Casing/liner Contractor |
Drilling Supervisor |
Confirm casing/liner tally prior to landing including correct measurement of all joints |
Drilling Supervisor Operations Engineer |
Drilling Supervisor Operations Engineer |
Responsibilities for casing/liner testing and report preparation are listed in the following table:
Action |
Execution |
Quality Control |
Prepare casing/liner running report and cementing report form |
Drilling Supervisor |
Operations Engineer |
Test casing/liner |
Drilling/Cement Contractor |
Drilling Supervisor |
Final casing report |
Drilling Supervisor |
Operations Engineer |
Drilling Supervisor responsibilities:
- verifying that the correct size, weight, grade and connections as per the Drilling Programme have been delivered
- independently measuring the casing and ensuring that no differences exist in the casing tally as measured by the Drilling Contractor
- counting the total number of joints and comparing this number with the casing tally, shipping manifest and number of joints remaining on site
- keeping a record of the total joints on locations and joints on the rack prepared for running
- numbering the casing joints in running order
- preparing the Casing Running Programme
- Checking stock of cement and additives and verifying in advance that stocks are available for the casing job
- ensuring that all running tools are in good, safe condition and are of the correct rating for the job
- Make-up torque of casing/liner
- Baker-lok shoe as per program
- Running speed of casing /liner
- Filling casing as it is RIH
- Drag in open hole
Drilling Contractor responsibilities:
- checking the side door elevators for uneven wear on the bearing surface and correct operation of the door latch, (single joint elevators shall be checked by trial latching before the casing is run. Grinding of elevators is dangerous and forbidden.)
- checking spider and elevator slips for size, condition and ability to operate evenly
- spider elevators and slips to have rating of casing weight in mud
- verifying load capability of drilling line.
- removing casing protectors, cleaning and checking threads, (pin and box ends shall be lubricated with the required lubricant and the thread protectors replaced hand tight)
- drifting the casing with a proper API drift
- measuring and numbering the casing during racking, (each layer shall be measured prior to accepting additional layers of casing)
- performing a safety check prior to use of stabbing board. This shall be performed with a checklist developed for each individual installation. The checklist shall be signed by the Drilling Supervisor
- installing bow/rigid centralizers
- rigging up circulating head, pressure testing cement lines.
Casing Running Contractor responsibilities:
- physically running the casing
- applying the correct make-up torque to the connections, (the make-up torque shall be approved by the Drilling Supervisor prior to casing running)
- verification and rig up of handling equipment including the JAM unit
- applying casing dope and baker-lok.