When dealing with areas of formation instability it is necessary to:

– trip cautiously through swelling formations

– pick up and ream midway through each stand (if hole conditions are severe, more frequent reaming may be required)

– trip through tight sections using slow rotation and circulation (after pulling into a tight spot, run back into gauge hole and circulate before back reaming out)

– ensure that sections of the hole found to be tight on the way out are always reamed on the trip back in.

– increase MW to maximum allowable for sloughing shales

– increase YP to avoid settling cuttings around the BHA

Note:    If drag is indicated after a connection, the joint should be reamed twice.