Well Planning Information Sheet, Well Datasheet, Well Design Information. This is the list of information required by the drilling department to plan and design a well.

 

BLOCK / LICENCE

 

 

WELL NAME

 

 

WELL CLASSIFICATION

 

 

PARTNERS (with %’s )

 

 

COMMITMENTS/LICENCE CONSTRAINTS

–      Spud Date

–      Completion Date

–      Other Timing Constraints

–      Total Depth

 

 

PROPOSED SPUD DATE

 

 

UNITS OF MEASUREMENT

–      Depth (feet or meters)

–      Referenced to (MSL, LAT)

 

 

TARGET LOCATION

–      Seismic line

–      Shot point

–      Coordinates UTM

 

–      Surface Location Accuracy

–      Water Depth

–      Site Survey

 

 

TARGET SIZE / BOUNDARIES

 

 

OBJECTIVES

–      Primary Objectives

Name

Lithology

Depth

Thickness

Type of Fluids

Gradient/Gravity

H2S / CO2 / Chlorides ( ppm )

Target Tolerance

Hole angle constraints

 

–      Secondary Objectives

Name

Lithology

Depth

Thickness

Type of Fluids

Gradient/Gravity

H2S / CO2 / Chlorides ( ppm )

Target Tolerance

Hole angle constraints

 

GEOLOGICAL SEQUENCE

–      Geological sequence showing range of possible interval thicknesses and depths, and any uncertainties.

 

 

PRESSURE PROGNOSIS

–      Include actual reservoir pressure

–      Potential for overpressure

 

 

FORMATION STRENGTH PROGNOSIS

 

 

TEMPERATURE GRADIENT

 

 

FORMATION DIP

–      Dip angle and direction for all intervals

 

 

TOTAL DEPTH

–      Definition (e.g. 20 ft into basement)

–      TD core required

 

 

CORING REQUIREMENTS

–      Coring Policy (on shows etc )

–      Possible cored intervals

–      Estimated No. and thickness of cores

–      Restrictions on core size

–      Special requirements (oriented core, fibre glass inner barrels, low invasion system, etc.)

 

 

SAMPLING REQUIREMENTS

 

 

ELECTRIC LOGGING REQUIREMENTS

–      Top Hole Section”

Logs required

Optional logs

No. of runs

Estimated duration

 

–      Intermediate Hole Section

Logs required

Optional logs

No. of runs

Estimated duration

 

–      Reservoir Hole Section

Logs required

Optional logs

No. of runs

Estimated duration

 

–      Cased hole logging

Logs required

Estimated duration

 

–      Hole size restrictions / preferences

–      Constraints on drilling mud properties

–      Rathole req’d below last depth of interest

–      Log Data Transmission Requirements

 

 

VSP REQUIREMENTS

–      Type of survey ( VSP / check shot )

–      Estimated duration

–      Special requirements

 

 

TESTING REQUIREMENTS

–      Type of test

–      Testing Policy / Objectives

–      Hole / csg size restrictions / preferences

–      Est. No. and duration of tests (AFE )

–      Possible stimulation ( acidise, frac )

–      Testing fluid

–      Drilling mud tracer requirements

–      Depth correlation markers in casing

–      Wellhead / Tree requirements

–      Flaring requirements

–      Rathole required below test interval

 

 

POTENTIAL DRILLING PROBLEMS

–      Surface gas (Shallow seismic )

–      Overpressure

–      High Temperatures

–      H2S & CO2

–      Hole stability (Reactive shales,….)

–      Abrasive formations

–      Faulting

–      Hard stringers ( chert, quartzite,  etc )

–      Restrictions on bit types ( PDC )

 

 

DISCOVERY / APPRAISAL DRILLING

Sidetracking Option

Additional well(s)

Wellhead / Tree heights

Abandonment/Suspension Procedures

 

 

OFFSET WELLS

The following list is required (useful) for each offset well:

–      Mud logs

–      Composite logs

–      Pressure detection logs and tests

–      Drilling completion reports

–      Daily drilling reports

–      Daily geological reports

–      Any drilling related reports, mud recaps, IADC reports etc

 

 

 

 

 

 