– weatherford – 2 tongs & power units. Both 20” and 13/38
– rio negro grouted
– drains / channels preferably clear prior to spotting equipment
– 40” casing to cut. And corregate walls on cellar, cut out
– cellar to empty to locate the flyge pump sump. Install pump and hook up same
– mouse hole and rathole, in place
– pipe bins in place
– casing in place and strapped. All casing running tools ready
– chicksans connected to stand pipe, at subbase
– flare line. & degasser hooked up
– baryte recovery line hooked up
– stairs on pits installed
– trip tank pump
– totco wire line unit ready to go
– general rig floor rig up, tongs..etc
– totco geolograph recorder
– drilling line spooler
– primary check on bop’s
– spud mud ready + extra water in other tanks
– cementing ready, all lines rigged up silo’s full
– mudlog ready
– solids control ready
– barytes on location, silo’s full
– trash bins in plac
– pick up & make up two stands of hwdp & set in mast
– stab in tool checked, d/p centralisers
– false rotary. Etc
– 20” strapped + cleaned. Check stab in tool required
– channels cut in shoe + shoe made up on first joint run
– welding equipment ready + on stand by
– riser chains ready
– wooden mats out for drilling tools
– spacer spool installation on the bottom of 13 5/8 bops
– wash down guns rigged up
– install submersible pump in water pit and hook up and test same
– water well generator still on independent power
– weighted bucket on choke manifold flare line
– handrails to install between brine pit and obm tank walk way
– electrical panel to close at brine skid
– cable tray covers to install
– trip tank hose to hook up
– flow line to hook up
– bha to lay out and strap
– 20” casing to lay out and strap – i nstall shoe and cut out channels
– crown ‘o’ matic to install
– respot drill line spooler skid
– remove bop work platform to other side
– spreader beams on rig cantilever to remove and stow away
– open drainage channels from cellar deck to rio negro
– casing stabbing board to install and test
– lay out 20 riser by racks – check all turnbuckles and chains are working and lubricated
– hook up choke line to manifold – if you have time
– general drilling tools and casing to get ready
– have the 3 1/2 “ rams been replaced by 5”?
– 40” casing to cut off level with ground. Cut slots in cellar wall
– jet line to install
– check all chains and turnbuckles are functioning for holding down the 20” casing
– 20 casing to lay out, clean and measure and shoe to install. Channels to cut in shoe joint
– bha to lay out, rabbit and measure. Record stabilizer blade gauges.
– drains and ditches to clear of all obstructions
– rio negro. Is the chute properly installed to carry cuttings away?
– cable tray covers to install
– totco barrel on slick line
– geolograph hooked up
– submersible pump at waterpit to install and hook up – test same
– flare line off choke manifold to hook up
– poor boy degasser line to complete.bop platform on back side to install so flowline can be hooked up on surface pipe.
– 2 stands of hwdp in derrick prior to spud
– koomey unit to install at location
– ditches between pits to grout with old cement
– ensure the flowline to derrick shakers is clean, to allow the flow of cuttings to the end derrick shaker
– Prior to acceptance pressure test the rig pumps against kelly to 3000psi each pump, just to check the integrity of the connections.
– Cut a few of meters of formation to test the whole system (1x kelly down).