– weatherford – 2 tongs & power units. Both 20” and 13/38

– rio negro grouted

– drains / channels preferably clear prior to spotting equipment

– 40” casing to cut. And corregate walls on cellar, cut out

– cellar to empty to locate the flyge pump sump. Install pump and hook up same

– mouse hole and rathole, in place

– pipe bins in place

– casing in place and strapped. All casing running tools ready

– chicksans connected to stand pipe, at subbase

– flare line. & degasser hooked up

– baryte recovery line hooked up

– stairs on pits installed

– trip tank pump

– totco wire line unit ready to go

– general rig floor rig up, tongs..etc

– totco geolograph recorder

– drilling line spooler

– primary check on bop’s

– spud mud ready + extra water in other tanks

– cementing ready, all lines rigged up silo’s full

– mudlog ready

– solids control ready

– barytes on location, silo’s full

– trash bins in plac

– pick up & make up two stands of hwdp & set in mast

– stab in tool checked, d/p centralisers

– false rotary. Etc

– 20” strapped + cleaned. Check stab in tool required

– channels cut in shoe + shoe made up on first joint run

– welding equipment ready + on stand by

– riser chains ready

– wooden mats out for drilling tools

– spacer spool installation on the bottom of 13 5/8 bops

– wash down guns rigged up

– install submersible pump in water pit and hook up and test same

– water well generator still on independent power

– weighted bucket on choke manifold flare line

– handrails to install between brine pit and obm tank walk way

– electrical panel to close at brine skid

– cable tray covers to install

– trip tank hose to hook up

– flow line to hook up

– bha to lay out and strap

– 20” casing to lay out and strap – i nstall shoe and cut out channels

– crown ‘o’ matic to install

– respot drill line spooler skid

– remove bop work platform to other side

– spreader beams on rig cantilever to remove and stow away

– open drainage channels from cellar deck to rio negro

– casing stabbing board to install and test

– lay out 20 riser by racks – check all turnbuckles and  chains are working and lubricated

– hook up choke line to manifold – if you have time

– general drilling tools and casing to get ready

– have the 3 1/2 “ rams been replaced by 5”?

– 40” casing to cut off level with ground. Cut slots in cellar wall

– jet line to install

– check all chains and turnbuckles are functioning for holding down the 20” casing

– 20 casing to lay out, clean and measure and shoe to install. Channels to cut in shoe joint

– bha to lay out, rabbit and measure. Record stabilizer blade gauges.

– drains and ditches to clear of all obstructions

– rio negro. Is the chute properly installed to carry cuttings away?

– cable tray covers to install

– totco barrel on slick line

– geolograph hooked up

– submersible pump at waterpit  to install and hook up – test same

– flare line off choke manifold  to hook up

– poor boy degasser line to complete.bop platform on back side to install so flowline can be hooked up on surface pipe.

– 2 stands of hwdp in derrick prior to spud

– koomey unit to install at location

– ditches between pits to grout with old cement

– ensure the flowline to derrick shakers is clean, to allow the flow of cuttings to the end derrick shaker

– Prior to acceptance pressure test the rig pumps against kelly to  3000psi each pump, just to check the integrity of the connections.

– Cut a few of  meters of formation to test the whole system (1x kelly down).

 